Understanding the Welding Procedure Specification (WPS)

Core of Standard Welding Procedure

인쇄용 교육자료이수 확인란 포함
오픈베타지금은 전부 무료로 보실 수 있어요

경력자용 심화 콘텐츠는 10월 6일까지 무료입니다. 이후에는 월 9,900원으로 전환돼요. 신입용 입문 콘텐츠는 종료 후에도 계속 무료입니다.

요금 안내 보기 →

🎯 학습 목표

  • Understand the components of a WPS/PQR (WPS/PQR)
  • You can read welding symbols on the drawings.

📚 경력 학습 콘텐츠

You will thoroughly learn the production of test pieces for welding procedure qualification tests (PQR), mechanical testing, and passing criteria.

WPS Cannot Stand Alone

Even if the WPS states "preheat 100℃, heat input 2.0 kJ/mm or less," there is no guarantee that condition is safe. There must be a record of actual welding, cutting, and bending tests conducted under those conditions. That is called PQR (Procedure Qualification Record, Procedure Qualification Record).

[Welding Test Implementation]  →  [Test Specimen Collection and Testing]  →  [PQR Recording]
                                              │
                                              ↓ Backing
                                           [WPS Issuance]
                                              │
                                              ↓ Using This WPS
                                        [Welder Qualification Test (WQT)]
                                              │
                                              ↓
                                          [Actual Product Welding]

A WPS without a PQR is not a document, but a wish. The first requirement during the main contractor and classification society audit is "show us the PQR that supports this WPS."

Understand the 3-Layer Structure

DocumentWhat is it RecognizingTarget
PQRWelding under these conditions produces performanceProcedure
WPSTherefore, weld like thisProcedure (Instruction Manual)
WQT / WPQThis person can perform the procedurePerson (Welder)

Even if a welder is qualified, if the company does not have a PQR, the welder cannot perform the joint. Even if there is a PQR, if there is no welder who has passed the qualification test under that procedure, the joint cannot be performed either. Both are required.

Essential Variables / Non-Essential Variables / Supplementary Essential Variables

A core concept in PQR. This is the standard to determine whether retesting is required when conditions change.

ClassificationWhen ChangedExample
Essential VariablePQR Retesting RequiredBase metal group change, welding process change, filler metal classification change, thickness range exceeded, significant drop in minimum preheat temperature, PWHT condition change
Non-Essential VariablePossible with WPS revision onlyImproved weld shape details, presence or absence of backing, cleaning method, weaving width, etc. (depending on standard)
Supplementary Essential VariablePromoted to essential variable when impact testing is requiredHeat input, position, upper temperature limit between passes, etc.

Position is treated differently by each standard

  • ASME Sec.IX: Position is generally a non-essential variable for groove welds. However, it becomes an additional essential variable when notch toughness (impact test) is required.
  • AWS D1.1 / ISO 15614-1: Position is managed as an recognized range item.

> If you don't know this difference and apply "ASME doesn't require position" to shipyard drawings, accidents can occur. Determine the applicable standard first, and then check the variable table of that standard.

PQR Test Sequence

1. Test Plan Development (pWPS creation) — Preliminary WPS, conditions are written in advance
2. Test Specimen Material Preparation — Ensuring MTC (Mill Test Certificate) is essential
3. Test Welding Implementation — If under inspection, the inspector must be present
4. Visual Inspection + Non-Destructive Testing (RT/UT, MT/PT)
5. Specimen Cutting and Machining — The sampling location is specified by the standard
6. Mechanical Testing (Tensile, Bending, Impact, Hardness, Macro)
7. Result Evaluation → PQR Creation and Signing
8. Issue WPS Based on PQR

Record the actual values used in step 3 exactly as they are. PQR is not a record of planned values, but a record of actual measured values. WPS is used for ranges, and PQR is used for a single value from that day.

Test Items and Evaluation

TestPurposeEvaluation Criteria (General Trend)
Tensile TestJoint StrengthMinimum tensile strength of base metal as specified. If the fracture occurs in the base metal and is at least 95% of the specified value, it is accepted (ASME)
Bending TestDuctility and Fusion ConditionNo defects exceeding 3mm on the convex surface after bending (ASME series). Edge cracking is judged separately
Impact Test (CVN)Low-Temperature ToughnessAverage of 3 samples at the specified temperature must be above the required value. ISO 15614-1 series allows 70% or more of the average required value for 1 sample
Hardness Test (HV10)Hardening of Heat-Affected ZoneFor carbon steel and low-alloy steel, the upper limit is often 380 HV10 in the welded condition and 320 HV10 after post-weld heat treatment
Macro TestPenetration, Fusion, ShapeNo cracks or fusion defects, and confirmation of fillet weld throat thickness
NDT (RT/UT/MT/PT)Internal and Surface DefectsAcceptance criteria according to the applicable standard

> The number and type of bending test specimens (surface bending, back bending, side bending) depend on the plate thickness. Thin plates use surface and back bending, while thick plates use side bending instead. Check the relevant standard table for the exact number (ASME Sec.IX QW-451, etc.).

What the Bending Test Reveals

The location where the specimen cracks during bending provides diagnostic information.

Location of CrackSuspected Cause
Center of Weld MetalPorosity, slag inclusion, filler metal incompatibility
Fusion Line (Bond Area)Poor fusion, insufficient heat input, insufficient cleaning of the root face
Heat-Affected ZoneHardening, hydrogen, insufficient preheat

Acceptance Range — How Far Does One Test Cover?

The practical value of PQR lies in its range. The key is whether a test conducted at 20mm thickness can be applied to 8mm thickness.

Thickness Range (Varies by Standard)

ASME Sec.IX Series
  Test Specimen Thickness T → Generally accepted up to 2T (thicker specimens have separate tables)
  Example) T = 20mm test → Covers up to about 40mm

ISO 15614-1 Series
  Multi-pass (Multi-run) Welding → Range specified as 0.5t to 2t
  Single-pass (Single-run) Welding → Narrower range
  Example) t = 20mm, multi-pass → Approximately 10 to 40mm

※ This is a conceptual explanation. When applying, always check the relevant standard table.

There is a well-known rule regarding pipe welding position acceptance range.

If accepted as 6G (45° fixed) → Covers all positions
2G + 5G combination → Covers a range similar to 6G
1G (rotating) only accepted → Can only be used for below

That's why it's beneficial to conduct the test under the most difficult conditions once. If accepted as 6G, it reduces the need for retesting for other positions later.

Classification Society Approval — One More Layer for Shipbuilding and Marine

Because Busan, Ulsan, and Gyeongnam have a high proportion of shipbuilding, marine, and plant industries, classification society (Classification Society) approval is an additional requirement. Rules from the designated classification society, such as Korean Register of Shipping (KR), must be followed.

ItemGeneral IndustryWhen Classification Society Applies
PQR TestingIn-house or certified testing institutionClassification society inspector attendance is often required
WPS ApprovalIn-house welding technical responsible personClassification society WPS approval is required
WelderIn-house qualification test or national qualificationClassification society approved welder qualification is required
Filler MetalStandard complianceClassification society approved filler metal only can be used
Base MetalMill Test CertificateClassification society approved steel (with classification society stamp)

> The most common mistake among subcontractors is not having classification society approval for filler metal. Even if the standard is the same, using products without classification society approval will result in rework due to lack of document recognition, even if the welding itself is fine. Obtain and keep the classification society certificate (Certificate) during the procurement phase.

Actual Issues Raised During Audits and Inspections

IssueDescription
WPS without PQRTaking another company's WPS and just changing the company name
Exceeding Thickness RangeConstructing a 30mm joint with a 10mm PQR
Filler Metal Classification MismatchNot knowing that the classification symbol changed when the brand changed
Arbitrarily Lowering Preheat TemperatureViolation of essential variable → Procedure invalid
Welder Qualification ExpiredMissing management of validity period and extension records
No Measured RecordsBlank pages for preheat and interpass temperature measurements
Missing PQR SignaturesNo signatures from test witnesses or technical responsible persons

PQR File Checklist

  • Conditions in pWPS (preliminary WPS) and PQR correspond to each other
  • Mill Test Certificate (MTC) for base metal is attached
  • Test report and approval certificate for filler metal is attached
  • Actual measured values for preheat and interpass temperature are recorded
  • Heat input calculation is based on actual measured current, voltage, and speed
  • Original mechanical test report from a certified institution or with witness is present
  • Recognized range (thickness, diameter, position, material group) is specified
  • Signatures and dates from test witnesses and technical responsible persons are present
  • A list of WPS numbers referencing this PQR is managed

🛠 실습 포인트

  • Practice in Writing WPS (Welding Procedure Specification) Forms
  • 10 Questions on Interpreting Welding Symbols on Drawings

🔑 핵심 용어

🔗 관련 모듈

TEAM AI ASSESSMENT

채용 전 검증, 입사 후 교육 — 팀 AI 역량, 숫자로 관리하세요

4영역 실측 팀 진단, 4주 실무 교육, 재진단 델타 리포트까지. 1인 3만원부터.

AQ 팀 진단·교육 알아보기